Street resurfacing within the City will continue next week. As a result, there will be no parking on the respective streets on the day(s) work is being done. Residents should plan accordingly. Contractors will also be providing in person notification to the addresses impacted. The schedule is as follows:
-Monday, July 7
Clayton Court, Pickleball Court
-Tuesday, July 8
Dorman Road, Woodland Drive north of Mountain View, Sherwood Avenue from cul-de-sac to dead end
-Wednesday, July 9
Edgwood Street from Bethany Pike to Woodlawn, East Park Street
-Thursday, July 10
Raven Avenue and Hawk Court
*Please note the schedule is subject to change daily depending on weather, production, mechanical breakdowns and specialty equipment scheduling conflicts. Thank you for your patience as we improve our streets.